Shipping a Complete Sulfur Recovery Unit in 25 Weeks

Customer challenges:

  • Inaccurate equipment measurements.
  • Delays cargo readiness.
  • Delivery schedule.
  • Cultural differences and general communication between supplier and importer.
  • Aligning shipment documentation according to the classification decision

Our solution:

  • Central communication & coordination.
  • Dedicated project team, onsite management.
  • Set up a temporary customs zone in the port of Nizhnekamsk.
  • Prepare shipment invoices following Russian customs requirements.
  • Guarantee (free of charge) deliveries on DDP terms and certification guidance

Project Overview

  • 25 weeks door-to-door delivery
  • multi-modal transport
  • 18000 Km
  • 13 chartered vessels and 900 trucks
  • 9 loading points and 10 trading lades
  • 170 containers
  • 350 oversized units
  • 7 countries (Asia and Europe)