Some figures:

  • Total investment: € 11,9 million
  • 46.237 m2 load surface area
  • 24.500 m2 warehouse surface area (frost free)
  • 5.600 number of pallet positions
  • 16 docking pits and 8 gates

Milestones:

  • 14/01/02: Architect's contract signed
  • 12/06/02: Building permit granted
  • 08/07/02: Environmental permit granted
  • 12/07/02: Land purchase
  • 17/10/02: Building contract signed
  • 04/11/02: Start of construction work
  • 11/07/03: Completion
  • 18/07/03: Move to new premises
  • 25/09/03: Official inauguration

For more info, please feel free to download the full leaflet from the Ahlers' Information board in our News section.

Some pictures of the festive inauguration on September 25th, 2003.

© January 2009 Ahlers.
Terms & conditions of use and privacy statement are set out in our Legal Disclaimer.